PILE INSTALLATION RECORD
Pile installations record is most part of pile
constriction if you are a civil site engineers then sure know about pile
installation record. If you are fresher civil engineer or supervisor and did
not know about pile installation record then we are teach you how to make pile
installation record.
Pile
installation record also known as Pile Pour card. Pile record maintain 3 basic
step.
- BASIC
DATA
- PILE
BORE DATA
- FLUSHING
RECORD
- CONCRETING
RECORD
BASIC DATA:-
1st
stage record basic data we are note dawn basic think like.
1. Pilling
layout Drawing No.
2. Pile
Number
3. Location
coordinates
4. System/
Structure
5. Pile
type: Vertical/Ranker
6. Pile
Nominal diameter
7. Pile
Tip Elevation
8. Pile
cut-off elevation
9. Ground
level at Pile location
10. Grade
of concrete specified
11. Reinforcement
details ( Draw sketch if complex )
12. Safe
capacity of pile specified
PILE BORE DATA
- Date and time pile bore start
- Date and time of completion
- Method of boring
- Inner nominal diameter of temporary casing/permanent liner
- Length of temporary casing/Permanent liner
- Material of permanent liner
- Method of jointing temporary casing/permanent liner
- Treatment to permanent liner
- Length bored in soil
- Length bored in rock (the rock shall be as defined in data sheet a or notes to schedule of quantities for purpose of measurement).
- Bore log and standard penetration tests (draw sketch or refer to separate sheet).
- Number of subsoil samples/rock cuttings collected
- Ground water elevation
- Any artesian conditions
- Any bore collapse and details
- Any loss of drilling mud and detail.
- Any other details or phenomena observed
FLUSHING RECORD
- Date or time of start of final post- bore Flushing
- Date and time of completion of final post-bore flushing.
- Remark on inspection of wash of post-bore flushing.
- Data and time of start of final pre- concreting flushing.
- Data and time of completion of final pre- concreting flushing.
- Remarks on inspection of wash of pre-concreting Flushing’s.
CONCRETING RECORD
- Date and time of start of concreting
- Date and time of completion of concreting
- Grade of cement and name of manufacturer
- Date of manufacture of cement.
- Grade of concrete as mixed
- Grade of concrete specified
- Slump of mixed concrete at pile head
- Cube test results.
- Method of concrete placement in pile bore
- Theoretical volume of concrete ( pile tip to top of pile as cast)
- Actual Volume of concrete : ( Pile tip to top of pile as cost )
- Ratio of actual volume to theoretical volume of concrete ( express as percentage )
- Any delay during concreting and reasons
- Overflow quantity
- Any other details
SIMPLE FORMAT FOR PILE INSTALLATION RECORDS
(COMPANY
NAME)
(COMPANY
ADDRESS)
POUR
CARD
CLIENT:
SL.NO :
PILE DIA :
PILE LOCATION :
1. BORING
DETAILS:
DATE OF BORING STARTED -
DATE OF BORING
COMPLETED -
DEPTH OF PILE -
2. REINFORCEMENT
DETAILS:
MAIN BAR BOTTOM CAGE16MM
DIA= 4nos.x 1.58kg x _______Mtr = kgs.
MAIN BAR TOP CAGE16MM
DIA= 4nos.x 1.58kg x
__________Mtr = kgs.
MAIN BAR BOTTOM CAGE12MM
DIA= 8nos.x 0.89kg x _________Mt = kgs.
MAIN BAR TOP CAGE16MM
DIA= 4nos.x 0.89kg x __________ Mtr
= kgs.
INNER RING 12MM DIA =
1.46Mtr x 0.89kg x
nos. = kgs.
Helicals 8mm dia =______/0.15 x 1.80mtr x 0.39kgs = kgs.
L- Beand 16mm dia= 4nos.x
1.58kg x 0.250Mtr = kgs.
L- Beand 16mm dia= 4nos.x
0.89kg x 0.250Mtr
= kgs.
Total= kgs.
3. Concreting
Details:
Grade of concrete
- M30
Date of concrete started -
Date of concrete completed -
Concrete Actual Quantity -